    ACUA recently installed a new 40 x 12 ft. enclosed flare at our landfill to help decrease odors and improve efficiency.

    FlareGif

    New Flare Going Up


    The flare is used to burn excess landfill gas that is not already used to generate electricity through ACUA’s existing landfill gas to energy project. It converts methane found in landfill gas into carbon dioxide, a less harmful greenhouse gas.

    The new flare will burn the excess landfill gas at a much higher efficiency than the older flare that was removed, which you can see through the images below had reached the end of its useful life. As a result, odors and emissions will be greatly reduced.


    OldFlare

    Old Fare Being Replaced


    The project cost approximately $440,000 and is representative of the infrastructure improvements being made across the Authority’s facilities.

    Over the past two years, ACUA has installed dozens of additional gas recovery wells to improve its landfill gas collection system as well as a temporary cap to cover open portions of the landfill. Both projects greatly improve gas collection efficiency and reduce odors.

    NewFlareOldFlare 

    FlareComparison

    Left: Old Flare, Right: New Flare in Place




    Click here to read more about how ACUA controls odors at the landfill.




    Bookmark and Share
     
 
Search Our Directory

© ACUA 2017 All Rights Reserved.