mobile logo

How ACUA is Preparing for the Next Sandy

Jan 14, 2015

By Sara Verrilo

During Hurricane Sandy, ACUA’s Wastewater Treatment Plant came within 6 inches of flooding. If the storm had been worse, crucial infrastructure may have been compromised. 

In preparation for the next storm, ACUA has applied to the New Jersey Environmental Infrastructure Trust, which provides low-interest loans for water and wastewater infrastructure projects, for the following resiliency projects:

Portable Flood Barriers

Portable flood barriers can be inflated for use during storms and other high water events at the Wastewater Treatment Plant and at off-site pumping stations. Estimated cost: $100,000.

Flood barriers
An example of portable flood barriers.

Sumps

Sumps will be installed in the lower elevated buildings of the plant would be used to remove water from powerful storm surges and prevent flooding from causing failure at the facility. Estimated cost: $300,000.
 

Seawall

A seawall would be built to surround sections of the facility that are not at a high enough elevation to withstand flooding (indicated in yellow below). The seawall will protect the plant from storm surges that could cause a failure during storms and high water events. DC Water is currently installing similar technology along its Blue Plains plant to protect flooding from the Potomac River. Estimated cost: $8,500,000.

 

seawall

The yellow outline shows the areas that would be guarded with a seawall.

 


seawall2

The second image shows an example of a completed seawall.

 

Once we receive authorization for these projects, we are expected to put them out for bid in the spring and begin construction by summer. The seawall project is currently going through the permitting process with various regulatory agencies before construction can begin.

We’ll keep you posted as the projects get underway.